Project Success?

Measuring Success What defines project success? On “time and budget”, or “to specification and quality requirements”, maybe all of these? No, we are missing some less tangible, but critical components; how do people feel about the project once it is done.

On May 12 the PMI-SAC Awards for the best projects and the best project managers will be held in Calgary and Captain James Lovell, Commander of Apollo 13 will be giving the keynote “Apollo 13 – A Successful Failure”. This year I am a judge for the awards ceremony and in reviewing the applicants I have been thinking about what constitutes a successful project which prompted the recollection of some famous projects...

Apollo 13
Let’s consider Apollo 13. The third manned mission by NASA intended to land on the moon that experienced electrical problems 2 days after liftoff. An explosion occurred resulting in the loss of oxygen and power and the "Houston, we've had a problem" quote from Lovell (that is widely misquoted as, "Houston, we have a problem".)

The crew shut down the Command Module and used the Lunar Module as a "lifeboat" during the return trip to earth. Despite great hardship caused by limited electrical power, extreme cold, and a shortage of water, the crew returned safely to Earth and while missing the main moon-based scope, it was a very successful rescue, allowing future missions. “A Successful Failure

Titanic
(The 1997 film not the original ship). This film was six months late, massively over budget and finished with a bloated 194-minute running time. Seemingly not a good performance given the original schedule, budget and scope requirements. Yet the film turned into an enormous critical and commercial success, winning eleven Academy Awards, including Best Picture and became the highest-grossing film of all time.

 

Continue reading "Project Success?" »


The Simple Guide to Earned Value

Earned Value How-To I have written a couple of posts now on agile alternatives to earned value, but lots of people still do not understand traditional earned value. So here is a simple worked example and a one page .PDF summary...

Let’s imagine our project is to build a wall around a garden. 
 
W1   

For simplicity, let’s assume 4 equal sides and a budget of $200 per side. Our schedule is one side per day so we should finish in 4 days with a cost of $800.

Here is how the project progresses:

Continue reading "The Simple Guide to Earned Value" »


Upcoming Events

2009 Calendar After returning from teaching a PMI class in New Orleans, the PMI have added some additional venues for the course later in the year. This is a good sign for agile methods within the PMI community; the course sold out quickly which hopefully indicates that many companies are still able to invest in training.

My 2 day Agile Project Management courses will be offered:

Of course PMI events go on throughout the year (full schedule), but this year I have deliberately kept the summer free from work events to enjoy some outdoor things closer to home. I am currently signed up for the Police Half Marathon, Calgary Marathon, Canmore 24hrs of Adrenaline, The Canadian Death Race, The TransRockies Bike Race, and Half Moon Adventure Race. Time will tell if I survive them all or stub my toe on the first one and miss the rest – hopefully not! I will report any remotely work related news back here.

Other agile events that look interesting this year include:
Atern Road Shows in the UK: London May 14, Bristol June 18, Manchester June 25.
XP 2009 Sardinia, Italy May 25-29
Agile 2009 Conference, Chicago August 24-28
Agile Business Conference, London October 13, 14

So many events, so little time!